September 9

Venture Global’s Plaquemines LNG gets OK to start cooldown activities

0  comments

[[{“value”:”

According to a FERC filling dated September 6, the regulator grated Venture Global Plaquemines LNG’s request to “introduce hazardous fluids to the jetty 2 and associated marine terminal transfer piping, LNG storage tank 1, BOG compressor system A, and temporary LP flare area, for the LNG storage tank 1 reverse cooldown activities.”

This approval is based on FERC staff inspections, and review of the information filed on July 29, August 13, 21, 23, 28, and 29, and September 3 and 5, 2024, it said.

The regulator also noted this approval does not grant Venture Global the authority to construct, commission, or introduce hazardous fluid to other project facilities at the LNG terminal.

Venture Global posted an image via its social media on August 23 of the 2020-built 174,000-cbm, Qogir, at the Plaquemines LNG export facility.

The company said in its August construction report filed with FERC that the LNG carrier docked at the second Plaquemines LNG loading platform (LP2).

According to Venture Global, it has completed jetty 2 loading arm commissioning.

This LNG carrier, owned by TMS Cardiff Gas and chartered by TotalEnergies, is laden with a cargo from Equinor’s Hammerfest LNG terminal in Norway, its AIS data provided by VesselsValue shows.

The vessel was on Monday located at the Plaquemines LNG facility.

LNG Prime previously contacted Venture Global to comment on the arrival of the LNG carrier and provide further information, but we did not receive a reply.

In April last year, Venture Global sought approval from the from the US DOE to export previously imported LNG from its terminal under construction in Plaquemines Parish in volumes of up to the equivalent of 600 million cubic feet of natural gas over a two-year period starting upon issuance of the authorization.

Plaquemines LNG sought this authorization to allow it to re-export natural gas imported to the terminal as part of the cool-down of terminal facilities during the start-up of those facilities.

The firm said it has determined that the optimal method for this part of the start-up of its terminal facilities is to import foreign sourced LNG by vessel and it may receive up to three LNG carrier cargoes for this purpose.

Plaquemines LNG expects that all of its LNG imports will occur this year, as part of its start-up operations.

Besides Qogir, Venture Global’s first LNG carrier, Venture Gator, was on Monday also located near the Plaquemines LNG terminal, its AIS data shows.

This 174,000-cbm LNG carrier appears to be empty and it may be used for re-export of the remaining volumes.

In June, Venture Global took delivery of this vessel in South Korea, the first of nine LNG carriers.

Venture Global LNG recently revealed in a FERC filling that it expects to start LNG production at its Plaquemines LNG plant in Fall this year.

According to Venture Global, the company’s second project has completed nearly 80 percent of the project’s construction.

Venture Global is targeting first production of LNG this Fall, with “exports of LNG ona pre-commercial operation basis beginning soon thereafter,” it said.

In April, the company said it expects to start LNG production at its Plaquemines LNG export plant in mid-2024.

Venture Global expects the commissioning process for the Plaquemines LNG terminal to take about 24 months.

Venture Global took a final investment decision in May 2022 on the first phase of the Plaquemines project with a capacity of 13.3 mtpa and the related pipeline. It also secured $13.2 billion in project financing.

In March last year, the company sanctioned the second phase of the Plaquemines LNG export plant in Louisiana and also secured $7.8 billion in project financing.

The full project, including the second stage, will have a capacity of 20 mtpa coming from 36 modular units, configured in 18 blocks.

Worth mentioning here, the US Pipeline and Hazardous Materials Safety Administration (PHMSA) recntly gave the green light to Venture Global LNG for its proposed Plaquemines LNG uprate project.

PHMSA issued a letter of determination on June 21 for the project aimed at increasing the peak liquefaction capacity at the Plaquemines LNG terminal from about 24 mtpa to 27.2 mtpa.

Venture Global’s Plaquemines LNG plant received in August last year its first liquefaction modules.

Baker Hughes ships these modular units to the US from its manufacturing facility in Italy, the same as the firm did for Venture Global’s Calcasieu Pass project.

In December, Venture Global LNG completed raising the roof on the fourth and final storage tank.

The firm completed raising the roof onthe first tank in February, the second tank in April, andthe third tank in September.

McDermott’s unit CB&I won a contract from a unit of Venture Global to build the first two LNG storage tanks as part of the first phase while the second phase includes two tanks as well.

Source: Lngprime.com

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post Venture Global’s Plaquemines LNG gets OK to start cooldown activities appeared first on Energy News Beat.

“}]]  


Tags


You may also like