The two units of state-owned PetroVietnam signed the LNG supply contract on November 19, according to a statement by PV Gas.
Regasifed LNG will be used for the commissioning of the Nhon Trach 3 and Nhon Trach 4 power plants.
PV Gas did not provide further information regarding the shipment.
The company recently released a new tender inviting firms to submit bids for one spot LNG cargo for delivery to its 1 mtpa Thi Vai LNG import terminal.
According to PV Gas, the delivery window for the partial LNG cargo is from December 20, 2024, to January 5, 2025.
PV Gas LNG, a unit of PV Gas, sought one LNG cargo of 2,500,000 million British thermal units (MMBtu) of LNG on a delivered ex-ship (DES) basis, and the tender closed on November 12.
PV GAS and PV Power are pioneering in supplying/using imported LNG to produce electricity to serve the country’s economic development, PV Gas said.
Besides investing in large-scale LNG power projects such as the Nhon Trach 3 and Nhon Trach 4 plants, PV Power is also converting power plants to use LNG, the company noted.
In November 2021, PV Power broke ground on the Nhon Trach 3 and 4 plants in the southern province of Dong Nai, which are worth about $1.4 billion.
Vietnam’s first LNG power plants will have a total capacity of 1.5 GW.
In September 2024, PV Gas said it plans to start commissioning its Nhon Trach 3 LNG power plant in October.
PV Power recently also signed a power purchase agreement (PPA) with a unit of Vietnam’s power utility EVN for the LNG power plants.
We give you energy news and help invest in energy projects too, click here to learn more
Crude Oil, LNG, Jet Fuel price quote
ENB Top News
ENB
Energy Dashboard
ENB Podcast
ENB Substack
The post PV Gas to supply commissioning LNG cargo to Nhon Trach power plants appeared first on Energy News Beat.
“}]]